TugAdvise logo
+44 (0)20 7929 0268
  • Home
  • About us
  • What we do
  • Who we work for
  • Team
  • Contact
  • Home
  • About us
  • What we do
  • Who we work for
  • Team
  • Contact

Take care in heavily mined waters

24th January 2017

This article looks at a court judgment under TOWCON and warns of the risk to tugowners of cancelling or withdrawing from a disputed contract

Take care in heavily mined waters

2016 has drawn to a close, and it was an interesting year. It also ended with a rare event: a court judgment under TOWCON. Before you get too excited and call your broker to start applying red tracked alterations to the standard wording, no ground breaking changes follow from the ruling. But as always there are useful lessons to be learnt.

You are welcome to plough through the 20 pages of the judgment if you have time, and there is plenty there to consider both in terms of how a contract was negotiated and performed, as well as how the parties fell apart and what legal traps they stumbled into. However, more likely your patience and time are limited so let’s distil it down to the key pointers that emerge.

The case dealt with a common problem of fixed sum tows: if it goes more slowly than anticipated, other than for weather delays, the tugowner is likely to be losing money, alternatively the hirer’s future planned use of the tow on arrival is in jeopardy. Questions arise whether the slow speed is down to the performance of the tug or something else.

We had one such case where the tow was a new hull. The hirers engaged a second tug at great expense and pressed for the additional cost also withholding the final lump sum instalment. The second tug, however, added only half a knot. It transpired that the unfinished hull had a number of openings in it and it was pretty obvious that these greatly affected the hull speed. The hirers climbed down and paid the hire.

The recent case involved a tow by Singaporean operated tug Harmony 1, a four engine, 13,000 bhp, 146 tonnes bollard pull, 1980-built but more recently modernised AHTS vessel.

It was contracted to tow an FPSO of 134,000 dwt, operated by a Swedish oil company, half way around the world. The contract provided that the tow be ‘in light ballast condition’, which is a relatively common stipulation.

The parties disputed what quantity of ballast amounted to light condition. The judge applied a previous 2006 Commercial Court judgment that light ballast condition is “concerned with ensuring physical fitness, primarily stability, for the tow’s voyage…”, that is the minimum ballast required for physical safety.

The hirers had indeed ballasted down for other good reasons on the advice of their naval architect, but this was found to be some 30,000 tonnes over light ballast condition on delivery, later reduced to about 10,000 tonnes.

Having won on that point, the tugowners failed to recover the claimed delay payments under clause 17(a)(ii) together with damages for the extra bunker costs because they could not demonstrate that the additional weight and draft had a material effect on the towing speed. In particular, the tow speed did not increase as a result of the deballasting of 20,000 tonnes.

The tugowners had furthermore anticipated 4.5 knots using two engines. It was held that they could not rely upon clause 17(a)(ii) as it required the tugowner to make a decision to slow steam because the tow could not be towed at the original contemplated speed. Here the tow could have achieved that average speed by using all four engines, but obviously at the expense of further fuel which tugowners were reluctant to incur.

TOWCON does not contain a standard provision as to the speed to be achieved, but the hirers counterclaimed that tugowners had in effect agreed a collateral term guaranteeing a speed of 4.5 knots and were liable in damages. That was rejected.

Finally the tow had stopped en route while the parties sought to resolve their differences. When they failed to do so the tugowners gave notice of cancellation and withdrawal. This was ill-advised and they were found to have wrongfully repudiated the contract.

As a result they were also liable in damages for the hirers’ net costs of employing a second tug to complete the tow.

So what lessons can be learnt? For starters any party contemplating terminating a contract is entering heavily mined waters: complex issues arise and it is essential to take legal advice.

Secondly, the more information that can be exchanged pre-contract the better to enable proper calculations as to speed and performance particularly when concerning complex hull forms.

Thirdly, don’t confuse ‘light ballast condition’ with towing warranty surveyors’ recommendations: they may be two very different things.

Finally, if the contract is keenly priced, as inevitably it is in this market, take great care to ensure that the downside risk of things going wrong is not additionally falling on to the operator, as that will simply guarantee that a loss is made.

Simon Tatham is a partner at Tatham & Co and founder member of the www.tugadvise.com service. He has more than 30 years’ experience of shipping law.

Reproduced with kind permission of International Tug & OSV magazine. View original article.

Sign up to our circularsCirculars

News

Court of Appeal throws out defence of sovereign immunity to a salvage claim

In the November/December 2022 issue of International Tug & Salvage, Simon Tatham examined an October Court of Appeal judgement that demonstrates salvors that strike silver should be compensated.   Read the article here – Maritime Law ITS Nov 2022   

Read More

Articles

Do not delay salvage contracting

16 May 2022 by Simon Tatham Regular columnist Simon Tatham examines a recent maritime accident report to highlight the risks of not taking the offered LOF The International Group of P&I Clubs (IG) has been working on what it calls its Salvage Delay Project, an independent study into the increasing tendency for delays in the take up…

Read More

How SCOPIC is used under LOF

Regular columnist Simon Tatham explains the process, benefits and pitfalls of invoking SCOPIC in salvage Salvage situations develop quickly, calling for rapid decision making by the parties involved. For the opportunist, occasional salvor and a shipowner faced with its first salvage dilemma, they with probably not have experience of Lloyd’s Open Form (LOF) salvage let…

Read More

  • Credits
  • Legal notice
  • Complaints

© 2023 TugAdvise

TugAdvise is a trading name of Tatham Law LLP
Tatham Law LLP is authorised and regulated by the Solicitor’s Regulation
Authority (SRA). SRA number 657564.